Chapter 22 · Part V, Projects: Advanced

Chapter 22: Sub-Panel Installation

Last updated Pro-only

Quick answer

A sub-panel is a smaller breaker panel fed from the main, used to provide breaker capacity in another location, a detached garage, workshop, finished basement, or addition. The critical rule: at a sub-panel, neutrals and grounds must be kept separated, not bonded like they are at the main. Feeder sizing depends on amperage (60A, 100A, 125A typical) and distance. Plan 8–20 hours for the work depending on trenching, panel work at both ends, and inspection coordination. Cost is $300–1500 in materials; the long-feeder portion to a detached structure is one of the strongest cases in this book for hiring out at least the heavy infrastructure.

BEFORE YOU START THIS CHAPTER

The work in this chapter carries materially more risk than anything in Parts III and IV. The specific risks of sub-panel installation include mis-bonded neutral and ground (a code violation that places objectionable current on the equipment grounding conductor); undersized feeder conductors that overheat under load; improper grounding electrode at a detached structure; and trenching strikes on existing buried utilities (call 811 before any excavation).

Permit and inspection are required in essentially all OKC-metro jurisdictions for the work in this chapter, regardless of the homeowner exemption. Do not begin without a permit on file.

If you haven't worked through Parts I and II yet, do that first, the diagnostic and code references you'll need are there.

Do not attempt the procedures in this chapter if any of the following apply to your home: aluminum branch circuit wiring (typically 1965–1972 construction); knob-and-tube wiring; a panel brand with documented failure-rate issues (Federal Pacific Stab-Lok, Zinsco, certain Challenger panels, none of these were formally recalled by the CPSC, but independent testing and industry consensus identify them as unsafe to add load to); evidence of prior unpermitted electrical work you cannot identify the scope of; water damage, rodent damage, or burn damage in or near the work area; or any condition that does not match what this chapter describes. In any of these cases, hire a licensed electrician.

If anything goes off-script, wiring you don't recognize, a step that doesn't match the procedure, or your gut saying "this isn't right", stop, leave it de-energized with conductors capped, and call. We do mid-project rescue work every day.

Proceeding past this notice reaffirms the assumption of risk and release in the front matter.

Welcome to Part V. The projects in this section are bigger in every dimension: more wire, more time, more code complexity, and (in most cases) genuinely more risk. We'll cover sub-panels, 240V circuit additions, EV chargers, generators, panel replacement, and solar. Each chapter includes an honest assessment of when DIY makes sense and when calling a pro is the better choice.

Let's start with sub-panels.

A sub-panel is a smaller breaker panel fed from the main panel, used to provide breaker capacity in another location: a detached garage, a workshop, a finished basement, an addition. Adding a sub-panel solves three problems simultaneously: it gives you more breaker space (your main panel might be full), it puts breaker access closer to where you'll be working with the loads, and it reduces voltage drop on long circuit runs from the main panel.

Estimated time: 8–20 hours depending on distance, trenching needs, and complexity. Cost: $300–1500 in materials. Permit required: yes, in essentially all OKC-metro jurisdictions. This is a permitted-work project regardless of homeowner exemption.

Soft pro-call nudge: A sub-panel for a detached structure, fed by a long underground run, is a project that combines trenching, conduit work, panel work at both ends, and inspection coordination. For most homeowners, it's a 2–3 weekend project. For a pro, it's typically a single day. If you're working under time pressure, or if the run involves trenching across hard ground or under a driveway, this is one of the strongest cases in this book for hiring out at least the heavy infrastructure portion. You can save time and headache while still being involved in the planning and decisions.

What a Sub-Panel Is and Isn't

A sub-panel is a panel that's fed from another panel (the "main"), not directly from the utility's service. It has the same physical structure as a main panel: a feeder cable comes in, connects to a main breaker (usually) or to feed-through lugs, and distributes power to branch breakers.

The big differences between a main panel and a sub-panel:

  • Sub-panel doesn't have its own meter. All power flowing through the sub-panel is metered at the main panel.
  • Sub-panel's neutral and ground are isolated from each other. This is the rule that trips up DIYers most often. In a main panel, the neutral bar and ground bar are bonded together (usually by a green screw or strap). In a sub-panel, they must NOT be bonded. The neutrals and grounds get their own separate buses, and they're kept electrically separate.
  • Sub-panel is fed by a 4-wire feeder. Two hots, a neutral, and a separate ground. The neutral carries unbalanced current (the difference between the two hot legs); the ground is for safety only and shouldn't carry current.
  • If you discover an existing 3-wire feeder (two hots and a combined neutral/ground) at an older sub-panel: do not simply replace the panel without addressing the feeder. Older NEC editions allowed 3-wire feeders to detached structures under specific exceptions; recent editions have tightened these rules substantially. Retrofitting onto an existing 3-wire feed requires either pulling a new 4-wire feeder (the right answer) or navigating exception language that may no longer apply in your jurisdiction. This is a stop-and-call moment, not a substitution you can make in the field.

These rules are critical. Getting them wrong creates conditions where ground current flows through the sub-panel feeder's grounding conductor in normal operation, which is a code violation and a safety issue.

Main panel vs sub-panel: the bonding difference Two panel cutaways side by side. The main panel has the neutral bar and ground bar bonded together by a green bonding screw, this is the only place in the system where neutral and ground touch. The sub-panel has the neutral bar and ground bar isolated (no bonding screw, neutral bar floats on a plastic insulator), the four-wire feeder from the main panel keeps neutral and ground separated. MAIN PANEL Neutral and ground bonded together NEUTRAL GROUND BONDING SCREW Green, required, installed FROM UTILITY To ground rod SUB-PANEL Neutral and ground kept isolated NEUTRAL (floating) GROUND NO BONDING SCREW Removed · bars stay separated 4-WIRE FEEDER FROM MAIN To ground rod (detached structure only)

Sizing the Sub-Panel

Two questions: how many breakers do you need, and how much amperage do you need?

Breaker count: count the circuits you plan to feed from the sub-panel:

  • Detached garage workshop: maybe 4–6 circuits (lights, outlets, garage door, EV, big tool)
  • Finished basement: 6–10 circuits (lights, outlets, hardwired devices)
  • Addition: 4–8 circuits (lights, outlets, AC unit, etc.)

Add 50% for future expansion. A 12-space sub-panel with current need for 6 circuits is about right.

Amperage: the sub-panel's main breaker (or feed-through) sets the maximum current. Common sizes:

  • 30A sub-panel: small, for a couple of circuits
  • 50A or 60A: typical for a workshop or moderate detached structure
  • 100A: full-featured detached garage or significant addition
  • 125–200A: large additions, ADUs, or workshops with heavy loads

Calculate your expected total load and add safety margin. A sub-panel that runs at 80% capacity continuously is appropriately sized; one that runs at 30% is oversized but cheap to install once.

For most home workshops or finished basements, a 60A or 100A sub-panel is the sweet spot.

Materials

For a typical 60A sub-panel installation in a detached garage 50 feet from the main:

  • 60A 8-space (or 12-space) sub-panel with main breaker
  • 50 feet of 6/3 NM-B for indoor runs, or 6/3 SER for sub-panel feeders, or 6/3 UF-B for direct burial outdoor runs
  • 2 ground rods (8 feet long, copper-clad steel)
  • Acorn clamps for ground rod connections
  • 6 AWG bare copper wire for grounding electrode conductor
  • PVC conduit for any exposed sections
  • Conduit fittings, sweeps, glue, etc.
  • 60A breaker for the main panel (matched to your panel brand)
  • Permit
  • Cable connectors for both panel ends

Total materials cost: $400–700 for a typical detached-garage sub-panel.

For longer runs or higher amperage, costs scale up:

  • 100A sub-panel: 4/3 wire (significantly more expensive than 6/3)
  • 200A sub-panel: 2/0 or 3/0 wire (very expensive)
  • Long underground runs: deeper trenching, more conduit, more wire

Step-by-Step: 60A Sub-Panel to a Detached Structure

Let's walk through a representative project: 60A sub-panel in a detached garage, 50 feet from the house, fed via direct burial UF-B cable.

STEP 1: PLAN THE ROUTE AND PULL THE PERMIT

  1. Lay out the cable route from main panel to detached structure.
  2. Identify trench location, depth, and any obstacles (water lines, gas lines, septic field).
  3. Call 811 (Oklahoma One-Call) before digging. They mark utility lines for free; you must call at least 2 business days before digging. Skipping this and hitting a buried gas or electrical line is a serious safety incident plus expensive damage.
  4. Pull the permit.
  5. Submit any required plans (sub-panel size, feeder size, route).

STEP 2: TRENCHING

  1. Rent a trencher ($50–100/day) for runs over 30 feet. For shorter runs, hand-digging is feasible but tedious.
  2. Trench to 24" depth (UF-B requires 24" minimum cover; deeper is better in OKC clay soil).
  3. Smooth trench bottom to remove sharp rocks.
  4. Add a layer of sand or fine soil at the bottom (1–2") to bed the cable.
  5. If the run crosses under a driveway, sidewalk, or other obstacle: - For driveways: bore under or trench through (driveway repair after). - For shorter obstacles (sidewalks): a long pipe driven horizontally underneath can carry the cable.
Sub-panel trench: main panel to detached structure Side elevation cross-section of a 60-amp sub-panel feeder. The cable exits the house main panel, drops down inside the wall, exits the foundation in PVC conduit, sweeps into a trench 24 inches below grade, runs 50 feet underground to the detached garage, sweeps back up the garage wall in PVC conduit, and enters the sub-panel. Two ground rods at the detached structure are bonded to the sub-panel ground bus. Sub-panel feeder trench: main to detached 60A feeder, ~50 feet, 24 inches deep, conduit stubs at each end HOUSE MAIN PANEL DETACHED GARAGE SUB PANEL 2 GROUND RODS 8 ft, bonded 24″ min. cover ~50 FT UF-B FEEDER (4-WIRE) PVC PVC RULE UF-B is rated for direct burial, no conduit needed below grade. Use PVC only where the cable is exposed above ground or through the foundation.

STEP 3: INSTALL CONDUIT STUBS

Where the cable transitions from underground to above-ground, install PVC conduit:

  1. At the main panel (house) end: vertical PVC conduit rising from the trench up the side of the house, with a 90-degree sweep. The conduit enters the house through a knockout in the panel or an adjacent box.
  2. At the sub-panel (garage) end: vertical PVC conduit rising up the side of the garage, with a sweep into the garage wall, terminating at a knockout in the sub-panel.

The conduit protects the cable where it's exposed. Below ground, UF-B is rated for direct burial without conduit; above ground or where exposed, conduit is required.

STEP 4: PULL THE FEEDER

  1. Lay the UF-B (or SER) cable in the trench, with extra slack at each end (4–6 feet at each end is reasonable).
  2. Feed the cable up through each conduit stub.
  3. Inside each panel, allow enough slack for proper routing to the connections.

STEP 5: DRIVE GROUND RODS AT THE SUB-PANEL

Per code, a sub-panel feeding a separate structure typically needs its own grounding electrode (ground rod) system at the sub-panel. (For a sub-panel within the same structure as the main, the main panel's grounding is adequate.)

  1. Drive two 8-foot ground rods at least 6 feet apart, at the base of the structure where the sub-panel is.
  2. Use a rotary hammer with a ground rod driver attachment, or a sledgehammer (much harder).
  3. Ground rods should be driven flush with the soil surface or slightly below.
  4. Connect the rods together using 6 AWG bare copper wire and acorn clamps.
  5. Run the 6 AWG wire from the ground rod system to the sub-panel's ground bus.
Detached structure ground rod system Two 8-foot copper-clad ground rods driven into the soil at least 6 feet apart at the base of a detached structure. A length of bare 6 AWG copper wire connects the two rods using acorn clamps at the top of each rod. The bonding wire then continues up the side of the structure and into the sub-panel, terminating on the sub-panel's ground bus. Rod heads are driven flush with grade. The diagram shows the assembly at scale with depth and spacing dimensions. Ground rod system at a detached structure Two 8-foot rods, 6 feet apart, bonded with bare 6 AWG copper to the sub-panel ground bus DETACHED STRUCTURE WALL SUB PANEL GROUND BUS ROD 1 8 ft copper-clad steel ROD 2 8 ft copper-clad steel ACORN CLAMP approved for direct burial; bolts the bare 6 AWG to the rod 6 FT MIN 8 FT below grade BARE 6 AWG COPPER bonds rods and runs to ground bus RULES • Two 8-foot rods minimum • 6 feet apart minimum • Rod heads flush with grade • Bond with bare 6 AWG copper • Use acorn clamps, not splices • Run to sub-panel GROUND bus   (not neutral) REQUIRED FOR DETACHED

STEP 6: CONNECT THE SUB-PANEL

  1. Verify the sub-panel is wired correctly: ground bar isolated from neutral bar. Most sub-panels ship with a "neutral bonding screw" or "bonding strap" installed; for sub-panel use, this MUST be removed. Re-read the panel's instructions to identify the bonding component and confirm it's removed.
  2. Mount the sub-panel on the wall at the planned location.
  3. Bring the feeder cable into the panel through the conduit stub and a cable connector.
  4. Strip the cable's outer jacket so 6–12" of conductors are exposed inside.
  5. Make the connections inside the sub-panel: - Black hot wire to one of the main breaker's terminals (or feed-through lug L1). - Red hot wire to the other main breaker terminal (or feed-through lug L2). - White neutral wire to the neutral bus (NOT to the ground bus). - Bare/green ground wire to the ground bus (NOT to the neutral bus). - Ground rod conductor to the ground bus.
  6. Tighten all connections firmly.
  7. Install the sub-panel's dead front cover.

STEP 7: CONNECT THE MAIN PANEL END

  1. Turn off the main breaker at the main panel. Three-test verify the bus is dead.
  2. Bring the feeder cable into the main panel through the conduit stub and a cable connector.
  3. Strip the cable's outer jacket so 6–12" of conductors are exposed.
  4. Install a 60A double-pole breaker in the main panel. (Double-pole because it serves a 240V feeder.)
  5. Connect the wires: - Black hot to one terminal of the new 60A breaker. - Red hot to the other terminal of the 60A breaker. - White neutral to the main panel's neutral bar. - Bare/green ground to the main panel's ground bar.
  6. Verify connections, install dead front cover.

STEP 8: BACKFILL THE TRENCH

  1. Lay caution tape ("warning: buried electric line below") about 8–12 inches above the cable. This warns future diggers.
  2. Backfill carefully, avoiding sharp rocks near the cable.
  3. Compact the soil to avoid future settling.

STEP 9: ADD BRANCH CIRCUITS TO THE SUB-PANEL

Now the sub-panel has power, but no branch circuits yet. Add the circuits you planned:

For each circuit:

  1. Run cable from sub-panel to its destination (lights, outlets, etc.).
  2. Install breakers in the sub-panel.
  3. Wire branch circuits per Chapter 17's procedure.

STEP 10: INSPECTIONS

Schedule and pass:

  • Trench inspection (BEFORE backfilling) if required by your jurisdiction
  • Rough-in inspection for any new branch circuits
  • Final inspection after everything is energized and operational

For the trench inspection specifically: don't backfill until the inspector approves the cable depth and routing. Some cities are strict about this.

The Most Common DIY Failure: Neutral and Ground Bonding

The single most common code violation on DIY sub-panel installs: leaving the neutral bonded to the ground at the sub-panel.

The sub-panel ships with a bonding screw or strap that connects neutral to ground. This is correct for use as a MAIN panel. For sub-panel use, this bonding must be removed.

Why does it matter? Because if neutral and ground are bonded at both the main and the sub-panel, ground current flows in normal operation, defeating the ground's purpose as a safety conductor. A fault that should be cleared by a breaker may not be cleared, because the imbalance the breaker needs to detect is masked by the parallel ground path.

This is a hidden problem. Everything appears to work. Lights light, outlets power things. But the safety system has been undermined.

If you're installing a sub-panel: read the panel's instructions to identify the bonding component, and confirm you've removed it. Then double-check before energizing. Some inspectors specifically test for this, but some don't, and it's a violation that often slips through inspection only to show up in a later forensic investigation.

Sub-panel bonding screw: remove it A close-up view of a sub-panel interior with the neutral bus on the left and the ground bus on the right. Two side-by-side panels show the wrong configuration and the correct configuration. In the wrong configuration, the green bonding screw is still installed and bonds the neutral bus to the panel's metal chassis, which would create a parallel ground path through the feeder. In the correct configuration, the bonding screw has been removed, leaving the neutral bus isolated from the chassis on its plastic insulator. The four-wire feeder lands as expected: two hots on the main breaker, neutral on the neutral bus, ground on the ground bus. Sub-panel: remove the neutral bonding screw Sub-panels ship with a screw bonding neutral to chassis; this must be removed for sub-panel use WRONG, SCREW INSTALLED Neutral bonded to chassis; creates a parallel ground path 60A MAIN NEUTRAL BUS GROUND BUS SCREW STILL IN bonds neutral to chassis CODE VIOLATION CORRECT, SCREW REMOVED Neutral floats on its insulator; feeder ground does its job 60A MAIN NEUTRAL BUS GROUND BUS PLASTIC INSULATOR isolates neutral from chassis CODE COMPLIANT KEY RULE Neutral is bonded to ground at the MAIN panel only, never at a sub-panel. Read the panel's manual to find the bonding screw or strap.

Sub-Panel in the Same Building

If your sub-panel is in the same building as the main panel (a finished basement, addition, etc.), the procedure is similar but with a few simplifications:

  • No ground rod system at the sub-panel (the main panel's grounding system serves both).
  • The feeder is run inside the building (no trenching, less or no conduit).
  • The 4-wire feeder rule still applies; neutral and ground are still separated at the sub-panel.

This is a much simpler project, and it's a more reasonable DIY undertaking. A 60A sub-panel in a finished basement, fed by a 6/3 NM-B cable from the main panel 30 feet away, is a one-day project for an experienced DIYer.

When to Hire Out

Strong signals that this project is over your head:

  • The main panel is full and adding a sub-panel requires a service upgrade.
  • The run involves boring under a driveway.
  • The detached structure is more than 100 feet from the main (longer runs have voltage drop calculations and may need larger feeder size).
  • The main panel is unfamiliar (not a major brand) or shows signs of damage.
  • You don't have a way to safely de-energize the main panel for the connection (some homes have unusual configurations that require utility involvement).

For these, hiring out (or hiring out for the heavy infrastructure with you doing the easier parts like installing branch circuits at the sub-panel) is sensible.

What's Next

Chapter 23 covers 240V circuit additions: dryers, ranges, water heaters, AC units, welders. Chapter 24 covers EV chargers (a hot topic). Chapter 25 covers generators. Chapter 26 covers main panel replacement. Chapter 27 covers solar.

SPARK SHARK SIDE NOTE

A sub-panel project is the kind of work where doing it wrong has long-term consequences that won't show up in a normal inspection. The neutral-ground bonding mistake we mentioned can persist for decades, undermining safety in ways no one notices until something else goes wrong. If you're going to DIY this, take your time, read the panel instructions twice, and verify your work multiple times before energizing. If you're not sure, this is the kind of project where a 30-minute consultation with a licensed electrician (around $100–150) can confirm your plan before you commit. Worth every penny.

FAQ

What's the difference between a main panel and a sub-panel?
A main panel is fed directly from the utility's service and has the main bonding jumper tying neutrals to ground. A sub-panel is fed from another panel and MUST keep neutrals and grounds separated, no main bonding jumper, no bond screw, separate neutral and ground bars. Getting this wrong is one of the most common DIY code violations.
Does a detached sub-panel need its own ground rods?
Yes, NEC 250.32 requires a grounding electrode system at any detached structure with a sub-panel. Usually means driving two 8-ft ground rods at the structure and bonding them to the sub-panel's ground bar.
Can I install a sub-panel myself?
The homeowner exemption legally allows it on your primary residence, but this is one of the projects in this book where the time/risk math is the worst for DIY. Pro install is typically $2000–3500 depending on scope; DIY saves a few hundred but adds 20+ hours and significant inspection risk. For most homeowners, hire it out.
Back to all chapters